锡兰电力局新任总经理视察中缆公司Polpitiya-Hambantota 220kV线路项目现场
The New CEB General Manager inspected CCC Polpitiya-Hambantota 220kV Line Project Sites
2021年8月29日,锡兰电力局(CEB)总经理、项目经理和斯里兰卡可再生能源局主席一行视察中缆公司承建的斯里兰卡Polpitiya-Hambantota220kV输电线路项目。
On August 29, 2021, the newly appointed General Manager (hereinafter referred as GM), Project Manager of CEB (hereinafter referred as PM) and the chairman of Sri Lanka Sustainable Energy Authority (hereinafter referred as SEA) inspected the Polpitiya-Hambantota 220kV transmission line project in Sri Lanka contracted by CCC.
CEB总经理认真听取了项目建设情况汇报,实地查看了项目施工进度,对公司克服疫情困难,在保证安全、保证质量的前提下,多措并举推进项目建设的工作能力和取得的成绩表示充分肯定,并对公司利用项目所在国人力资源,积极运用属地化管理推动海外项目可持续发展的经营理念表示赞赏,同时希望公司能够加入到CEB更多的建设项目中,促进双方进一步加大合作力度,实现互利共赢。
GM of CEB was briefed on the project construction progress, and inspected the construction site. He fully affirmed CCC’s working ability and achievements in advancing the project construction by taking multiple measures of overcoming the difficulties and ensuring safety and quality under the prevailing situation of COVID-19. He also expressed his appreciation for CCC’s contribution of using local human resources and the philosophy of actively using localized management to promote the sustainable development of overseas projects. Furthermore, CEB hopes that CCC can join in more projects of CEB to strengthen further cooperation and to achieve mutual benefit and win-win situation.
图1:CEB视察项目现场,视察人员包括:斯里兰卡可再生能源局主席(左一)、CEB项目经理(左三)、CEB总经理(右三)、中缆项目经理(右二)
Picture 1: CEB inspects the construction sites. Including: Chairman of SEA (first from left), Project Manager of CEB (third from left), General Manager of CEB (third from right), Project Manager of CCC (second from right)